Holmewood Site Investment Plans

This website provides information on Magnavale’s investment plans for our Holmewood cold storage facility in Chesterfield.

The website will be updated throughout the construction phase with project completion targeted for November 2024.

Planning consent, which can be viewed here was granted for the extension of the existing facility in August 2021 by North East Derbyshire District Council.

Map of the site

Hard landscape

PROPOSED SECURITY FENCE

Soft landscape

PROPOSED SEMI NATURAL WOODLAND
National Vegetation Classification semi-natural woodland type W10

Soft landscape

PROPOSED WILDFLOWER GRASSLAND

Hard landscape

PROPOSED SHEET PILED RETAINING WALL

Hard landscape

PROPOSED ACOUSTIC FENCE

Soft landscape

EXISTING WOODLAND TO BE RETAINED

Soft landscape

PROPOSED GRASSLAND (MOWN)

Soft landscape

PROPOSED TREES
Betula pendula (Silver Birch)
Sorbus aucuparia (Rowan)

Hard landscape

PROPOSED REINFORCED CONCRETE RETAINING WALL

Latest Updates


12th August 2024

Dear Local Resident,

Update on our previous letter;

The revised dates for for pouring and power-floating concrete are now Friday 16th, and Monday 19th till Friday 23rd of August.

No works will take place over the weekend (17th and 18th August).

Power-floating is a process used to help concrete set in the hardest and most durable form it can, which is necessary for industrial environment it will be used in.

Unfortunately, the process can be loud, and once started has to be continued until the concrete has set.

We are taking every opportunity to limit the disturbance during these works including erecting temporary screening in addition to the acoustic barriers already on site.

Weather conditions are expected to be good during this period and we’ll start as early in the morning as we can to help prevent the works running into the late evening. However, if you have any immediate concerns, please contact us via the dedicated phoneline which will now be available via the Magnavale Holmewood planning website from the 16th August.

Kind regards,

Amanda Cogan
Magnavale, Chief Operating Officer

31st July 2024

Dear Local Resident,

Progress on the expansion of our Holmewood facilities continues at a rapid pace, with completion expected to remain on schedule. The updated schedule of works can be found below under Construction Timeline (July 24)

We are taking every opportunity to reduce any disturbance caused by the construction and will continue to do so until completion. With that in mind we want to let you know about some concrete power-floating works that may cause some noise disturbance between the 12th and 17th of August.

Power-floating is a process used to help concrete set in the hardest and most durable form it can, which is necessary for industrial environment it will be used in. Unfortunately, the process can be loud, and once started has to be continued until the concrete has set.

We are taking every opportunity to limit the disturbance during these works including erecting temporary screening in addition to the acoustic barriers already on site.

Weather conditions are expected to be good during this period and we’ll start as early in the morning as we can to help prevent the works running into the late evening. However, if you have any immediate concerns, please contact us via the dedicated phoneline which will be available via the Magnavale Holmewood planning website from the 12th August.

Kind regards,

Amanda Cogan
Magnavale, Chief Operating Officer

Construction Timeline (July 24)

August 2024

  • Lighting for pedestrian footpath
  • Tarmac for pedestrian footpath
  • Main building lighting to be completed
  • Power-floating of concrete top slab

September 2024

  • Drainage to be completed
  • Fencing installed
  • Car Park landscaped
  • Installation of remaining internal racking
  • New transformers to be made live

October 2024

  • Electrical commissioning and testing
  • Top-coat of car park tarmac
  • Footpaths and signage installed
  • Preparing landscaped areas

Contact Us


Submit your comment